The Wolf Summit
About the project
Images of a swimming pool at the Wolf Summit where the rebar/iron motifs with Chemical anchor (epoxy adhesive) of AC500Phrm were installed because of the strength, the quality and many devices of the adhesive.
Photos from the area



Pisgat Ze’ev Swimming Pool – rebar dowels set in Chemfix100 epoxy
At the Pisgat Ze’ev swimming pool the rebar dowels were set in Chemfix100 epoxy. Two considerations justified epoxy rather than a fast adhesive: the dowels carry a permanent load, where sustained-load behaviour is the governing criterion, and the environment stays water-saturated for the life of the structure. Chemfix100 needs about 18 hours to reach full cure at 20°C — and in cold conditions, around 5°C, that stretches to roughly 60 hours, a figure that belongs in the programme rather than being discovered on site.